We are excited to share the most updated photos of our project. The foundation for both buildings is being poured. What a beautiful addition this will be for our campus.

Traffic Pattern Changes Due to Construction

  • Mobilization/material staging:  Week of 11/19/18 Traffic maintained from Mechanicsburg/Country Club Drive
  • Phase 1 Storm installation: 11/27/18 – 12/07/18 Mechanicsburg traffic redirected around north end of property
  • Phase 2 Storm installation: 12/10/18 – 12/14/18 Country Club Drive traffic redirected around north end of property
  • Water line relocation: 12/17/18 – 12/21/18 Country Club Drive traffic redirected around north end of property
  • Strip pad/parking for WC: 12/17/18 – 12/31/18 Country Club Drive traffic redirected around north end of property

Changes to plan will be communicated as needed.

Project Gallery

WVHL Construction Update

West View Healthy Living Construction

West View Healthy Living Construction Update

West View Construction Process

Construction area West View Healthy Living