We are excited to share the most updated photos of our project. What a beautiful addition this will be for our campus.
Traffic Pattern Changes Due to Construction
- Mobilization/material staging: Week of 11/19/18 Traffic maintained from Mechanicsburg/Country Club Drive
- Phase 1 Storm installation: 11/27/18 – 12/07/18 Mechanicsburg traffic redirected around north end of property
- Phase 2 Storm installation: 12/10/18 – 12/14/18 Country Club Drive traffic redirected around north end of property
- Water line relocation: 12/17/18 – 12/21/18 Country Club Drive traffic redirected around north end of property
- Strip pad/parking for WC: 12/17/18 – 12/31/18 Country Club Drive traffic redirected around north end of property
Changes to plan will be communicated as needed.