Traffic Pattern Change

Ground Breaking

Traffic Pattern Changes Due to Construction
Date:  11/12/18

  • Mobilization/material staging:  Week of 11/19/18 Traffic maintained from Mechanicsburg/Country Club Drive
  • Phase 1 Storm installation: 11/27/18 – 12/07/18 Mechanicsburg traffic redirected around north end of property
  • Phase 2 Storm installation: 12/10/18 – 12/14/18 Country Club Drive traffic redirected around north end of property
  • Water line relocation: 12/17/18 – 12/21/18 Country Club Drive traffic redirected around north end of property
  • Strip pad/parking for WC: 12/17/18 – 12/31/18 Country Club Drive traffic redirected around north end of property

Changes to plan will be communicated as needed.